• Right of first refusal in project financing: the ECJ's censure.

  • 09/02/2026

  • In its ruling of 5 February 2026, Case C-810/24, Section II of the CJEU held that the right of pre-emption granted to the promoter in project financing procedures—which entitles the promoter to match its offer to that of the successful tenderer and thus secure the contract—contravenes the principle of equal treatment set out in Articles 3(1) and 41(1) of Directive 2014/23.
    By allowing the promoter to match the terms offered by the initial successful tenderer who proved to be the least costly, the right of pre-emption allows the promoter, in violation of the principle of equal treatment, to optimize its offer in order to better compete with the offers of its competitors in the concession procedure in question.
    In particular, this right undeniably allows the promoter to modify its offer after it has been submitted, which is prohibited precisely by the principle of equal treatment.
    Furthermore, according to the Court, the right of pre-emption entails a restriction on the freedom of establishment, set off by article 49 TFEU, as it may dissuade economic operators from other Member States from participating in a project finance procedure.

More news

  • Legal nature of the COSAP and limitation period.
  • 20/10/2026

  • With ordinance n. 26576/2026, the Italian Supreme Court of Cassation clarified that the fee for the occupation of public spaces and areas (COSAP) constitutes a non-tax revenue of a proprietary ...